    摘要:

    在小麦收获时期,若遇到天气变化,小麦可收获时间窗会发生改变,若还按原调度方案,将造成大量农田延迟收获,从而给农户带来损失。为避免或降低因天气变化给农户带来损失,本文考虑天气变化导致的农田收获时间窗变动的应急调度问题。基于天气变化导致的农田可作业时间窗实际缩短的情况,综合考虑收获机转移时间、提前到达等待时间和延迟时间,建立因天气变化导致的时间窗变动的收获机多目标应急调度模型,引入农田收获应急度函数,确定应急农田,将可作业时间窗和下雨时间有交集的农田重新根据应急度排序进行优先调度。针对此模型特点对遗传算法进行改进,设计基于改进遗传算法的收获机应急调度算法,采用两级多段编码方式及单点交叉方式,使算法可以有效避免局部最优,能够很好地实现全局收敛。通过动态改变原收获机收获路线,为应急农田优先提供收获服务,从而提高农机合作社服务能力,减少农户损失。实例仿真结果证明了模型和算法的可行性。

    Abstract:

    In the wheat harvest period, when the weather changes, the wheat harvesting time window will change, if the original scheduling scheme is not adopted in a timely and efficient dynamic scheduling method, it will cause a large number of farmers to delay the harvest of farmland, which will bring huge losses to farmers. To avoid or reduce the loss of farmers caused by weather change, considering the emergency scheduling problem of farmland harvester time window change caused by weather change, an multi-objective emergency scheduling model considering the transfer time, waiting time and delay time of the harvester was established, it considered a shortened harvest time window caused by weather change, and an emergency degree function of farmland harvest was introduced to determine the emergency farmland. The farmland with the intersection of working time and rainy time would be prioritized according to the emergency degree. The genetic algorithm was improved according to the characteristics of this model by using two-level multi segment coding method and single point crossing method, so that the algorithm can effectively avoid local optimization and achieve global convergence. Based on the improved genetic algorithm, an emergency harvester scheduling algorithm was designed to achieve the priority of emergency farmland by changing the original harvester route dynamically, so as to improve the service capacity of agricultural machinery cooperatives and reduce farmer losses. Finally, an example was introduced to prove the feasibility of the model and algorithm.

    参考文献
    相似文献
    引证文献
引用本文

汪浩祥,曹光乔,闫子彤,陈聪.天气变化情形下基于动态时间窗的收获机应急调度技术[J].农业机械学报,2023,54(10):105-113. WANG Haoxiang, CAO Guangqiao, YAN Zitong, CHEN Cong. Emergency Scheduling of Harvester Caused by Change of Dynamic Time Window Due to Weather Change[J]. Transactions of the Chinese Society for Agricultural Machinery,2023,54(10):105-113.